Manage Stakeholder Engagement is in which Process Group?
Monitoring and Controlling
Planning
Executing
Initiating
executing
Which
... [Show More] model plots stakeholders in a 3D space: influence, impact, and power called?
Stakeholder cube
Scatter plot
Salience model
Venn diagram
stakeholder cube
Which of the following is NOT generated during the Plan Stakeholder Engagement process?
Stakeholder register
Stakeholder engagement plan
engagement assessment matrix
Strategies about stakeholders' involvement
stakeholder register
Which of the following is NOT an output of monitoring stakeholder engagement?
Issues resolved
Stakeholder engagement plan changed
Performance reports
Change requests
performance reports
Your friend, Jon is a project manager of another project at your company that shares some of the same resources as your project. What kind of influence does Jon have on your project?
Downward
Outward
Upward
Sideward
sideward
Stakeholder register is a Major Output of which Process Group?
Monitoring and Controlling
Initiating
Planning
Executing
initiating
The focus of the stakeholder management knowledge area is:
Managing stakeholder expectations
Controlling stakeholders
Stakeholder engagement
Stakeholder management
stakeholder engagement
Project business documents are input to which stakeholder process?
Plan Stakeholder Engagement
Monitor Stakeholder Engagement
Identify Stakeholders
Manage Stakeholder Expectations
identify stakeholders
You have just joined a project that has already been planned. You want to take a look at strategies to implement and actions to perform to facilitate creative stakeholders involvement in the project, such as making project decisions and doing project execution. Where you will look?
1. Stakeholders engagement assessment matrix
2. Mind mapping
3. The stakeholder engagement plan
4. Project stakeholder register
the stakeholder engagement plan
the focus of the stakeholder management knowledge area is:
1. stakeholder management
2. managing stakeholder expectations
3. controlling stakeholders
4. stakeholder engagement
stakeholder engagement
Project business documents are input to which stakeholder process
1. identify stakeholders
2. manage stakeholder expectations
3. plan stakeholder engagement
4. monitor stakeholder engagement
identify stakeholders
which of the following is an input to all the processes of stakeholder management.
1. project charter
2. communications management plan
3. resource management plan
4. stakeholder engagement plan
communications management plan
which of the following is not an output of monitoring stakeholder engagement?
1. performance reports
2. change requests
3. issues resolved
4. stakeholder engagement plan changed
performance reports
you have generated a project document named project communications that can be used in which of the following processes
1. manage stakeholder engagement
2. monitor stakeholder engagement
3. plan stakeholder engagement
4. distribute information
monitor stakeholder engagement
the salience model can be used in which of the following processes?
1. manage stakeholder engagement
2. monitor stakeholder engagement
3. plan stakeholder engagement
4. identify stakeholders
identify stakeholders [Show Less]