What is the importance of the definition of done?
a. It creates standardized work
b. It provides a way for Scrum Master to enforce quality
c. It
... [Show More] prioritizes the work of testers on the team
d. It creates a clear understanding of when items are complete - correct answer d. It creates a clear understanding of when items are complete
An organization is conducting their first Program Increment Planning session, and the new teams are asked to provide their capacity. Which three actions are part of the initial capacity planning process? (choose 3)
a. Add the points for all the recently completed Features and use that as a baseline for future capacity
b. Find a small story that takes about a day to develop and call it a one
c. Subtract one point for every team member's vacation day, public holiday or training day
d. Use eight points per person (adjust for part-time employees
e. Ensure product Owner / Product Manager approval for all capacity adjustments based on time
f. Compare final team capacity across all teams and make individual team adjustments - correct answer b. Find a small story that takes about a day to develop and call it a one
c. Subtract one point for every team member's vacation day, public holiday or training day
d. Use eight points per person (adjust for part-time employees
What are two examples of team-level events? (Choose 2)
a. Daily stand up
b. Program Increment Planning
c. Scrum of Scrums
d. Backlog refinement
e. System demo - correct answer a. Daily stand up
d. Backlog refinement
The goal is fast delivery process, ideally requiring little manual effort. What is one capability used to achieve this?
a. Quite releases
b. Nonfunctional requirements
c. Features toggles
d. Soft launches - correct answer c. Features toggles
The goal of the Product Owner is most closely aligned with which Agile Manifesto principle?
a. The highest priority is to satisfy the customer through early and continuous delivery of valuable software
b. Welcome changing requirements, even late in development
c. Business people and developers must work together daily throughout the project
d. Build projects around motivated individuals - correct answer a. The highest priority is to satisfy the customer through early and continuous delivery of valuable software
Which principle of the Agile Manifesto is most aligned with conducting a System Demo?
a. Welcome changing requirements, even late in development
b. The best way to convey information is a face to face conversation
c. At regular intervals the teams reflects on how to become more effective
d. Working software is the primary measure of progress - correct answer d. Working software is the primary measure of progress
What is the purpose of iteration goals?
a. To align the team members and the Product Owner (PO) to the mission
b. To hold the team accountable to their goals
c. To ensure the team accomplishes all the committed Stories each Iteration
d. To provide the baseline required for measuring the team's performance - correct answer a. To align the team members and the Product Owner (PO) to the mission
Which two aspects of the Continuous Delivery Pipeline require the most involvement from Product Management?
a. Continuous Exploration and Release on Demand
b. Continuous Integration and Continuous Deployment
c. Continuous Integration and Release on Demand
d. Continuous Exploration and Continuous Deployment - correct answer a. Continuous Exploration and Release on Demand
Which role is primarily responsible for working with business teams?
a. Release Train Engineer
b. Enterprise Architect
c. Product Management (PM)
d. Product Owner (PO) - correct answer c. Product Management (PM)
Which Agile Team event supports relentless improvement?
a. Iteration Retrospective
b. Iteration Review
c. Iteration Planning
d. Backlog refinement - correct answer a. Iteration Retrospective
What are two primary responsibilities of Business Owners in Program Increment (PI) Planning? (Choose 2)
a. To create Lean business cases
b. To set the business context
c. To ensure that team members plan all of their priorities
d. To assing business value
e. To establish the PI budget - correct answer b. To set the business context
d. To assing business value
What is the relationship between a Produc [Show Less]