Acceptance Criteria - CORRECT ANSWER A set of conditions that is required to be
met before deliverables are accepted.
Accepted Deliverables - CORRECT
... [Show More] ANSWER Products, results, or capabilities
produced by a project and validated by the project customer or sponsors as meeting
their specified acceptance criteria.
Accuracy - CORRECT ANSWER Within the quality management system, blank is an
assessment of correctness.
Acquire Project Team - CORRECT ANSWER The process of confirming human
resource availability and obtaining the team necessary to complete project activities.
Acquisition - CORRECT ANSWER Obtaining human and material resources necessary
to perform project activities. Blank implies a cost of resources, and is not necessarily
financial.
Activity - CORRECT ANSWER A distinct, scheduled portion of work performed during a
course of a project.
Activity Attributes - CORRECT ANSWER Multiple blank associated with each schedule
activity that can be included within the activity list. Blank include activity codes,
predecessor activities, successor activities, logical relationships, leads and lags,
resource requirements, imposed dates, constraints, and assumptions.
Activity Code - CORRECT ANSWER One or more numerical or text values that identify
characteristics of the work or in some way categorize the schedule activity that allows
filtering and ordering of activities within reports.
Activity Cost Estimates - CORRECT ANSWER The projected cost of the scheduled
activity that include the cost of all resources required to perform and complete the
activity, including
all cost types and cost components.
Activity Duration - CORRECT ANSWER The time in calendar units between the start
and finish of a schedule activity.
Activity Duration Estimates - CORRECT ANSWER The quantitative assessments of the
likely number of time periods that are required to complete an activity.
Activity Identifier - CORRECT ANSWER A short, unique numeric or text identification
assigned to each schedule activity to differentiate that project activity from other
activities. Typically unique within any one project schedule network diagram.
Activity List - CORRECT ANSWER A documented tabulation of schedule activities that
shows the activity description, activity identifier, and a sufficiently detailed scope of work
description so project team members understand what work is to be performed.
Activity Resource Requirements - CORRECT ANSWER The types and quantities of
resources required for each activity in a work package.
Actual Cost (AC) - CORRECT ANSWER The realized cost incurred for the work