LDR-201S NCOA Exam (New 2024/ 2025 Update) Questions and Verified Answers | 100% Correct| Grade A
QUESTION
MSgt Killian said, "To make sure that
... [Show More] everything is progressing as it should, a project manager needs to be able to effectively measure and communicate project progress."
MSgt Killian's comments BEST explain which of the following stages of project management?
Answer:
Monitoring
QUESTION
MSgt Landry said, "This project management stage is all about giving the project a relatively broad definition and establishing whether or not it is feasible."
MSgt Landry's comments BEST explain which of the following stages of project management?
Answer:
Initiation
QUESTION
MSgt Carlson said, "This is the beginning of the creative stage, where the carefully laid project plans are turned into tangible deliverables."
MSgt Carlson's comments BEST explain which of the following stages of project management?
Answer:
Execution
QUESTION
Your subproject work breakdown goes here. It shows how the project will be broken down into subprojects, the deliverables that will be produced by each subproject, and who is accountable for each deliverable.
This statement BEST describes which of the following parts of a Project Plan?
Answer:
Structure/Accountability
QUESTION
This is at the end of the project, which shouldn't run more than a page or so. It should outline the highlights of the project.
This statement BEST describes which of the following parts of a Project Plan?
Answer:
The executive Summary
QUESTION
Following resources, this part is next. There shouldn't be more than 10 to 13 total tasks on it, including the deadline date for the final deliverable.
This statement BEST describes which of the following parts of a Project Plan?
Answer:
The Milestone Schedule
QUESTION
Start by including this into your team composition table. In this table, list each project team member and his or her status (regular or ad hoc member) and each stakeholder and his or her status.
This statement BEST describes which of the following parts of a Project Plan?
Answer:
Resources
QUESTION
This is the first section of the detailed plan. You must write it down in description in which you describe the final deliverable in terms the customer can understand.
This statement BEST describes which of the following parts of a Project Plan?
Answer:
The Scope Plan
QUESTION
This includes bo [Show Less]