LORA Correct Answer: Level of Repair Analysis: LORA will ensure that operational readiness is achieved
... [Show More] throughout a system's life cycle in an optimal, least cost fashion. Starting the LORA process early in a system's development, and continuous evaluation throughout its life cycle, can ensure LORA influences the systems design and the maintenance planning by producing an effective support solution.
LORA considers: Correct Answer: Cost, performance, schedule, and supportability to aid in finalizing an effective and supportable design solution.
FTA Correct Answer: Fault Tree Analysis: Involves using deductive logic to determine the possible causes of a defined undesired operational result. It is a top-down failure analysis of a system that analyzes a series of lower-level events.
RCM Correct Answer: Reliability Centered Maintenance (RCM): consists of a systematic approach of analyzing system/equipment reliability and system safety data to determine the feasibility and desirability of preventive maintenance activities, to highlight maintenance problem areas for design review consideration, and to establish the most effective preventative maintenance program for a system/equipment.
Level of repair Analysis (LORA) Correct Answer: The objectives of performing a LORA is to ensure that operational readiness is achieved throughout a system's life cycle in an optimal, least cost fashion. Starting the LORA process early in a system's development, and continuous evaluation throughout its life cycle, can ensure a LORA influences the systems design and the maintenance planning by producing an effective support solution.
MTA Correct Answer: Maintenance Task Analysis (MTA): The identification of the steps, spares and materials, tools, support equipment, personnel skill levels as well as any facility issues that must be considered for a given repair task. Also include in the MTA are elapsed times required for the performance of each task.
The Four Prime factors that govern system acquisition programs are: Correct Answer: Cost, schedule, performance, and supportability.
Enclosure 6, Section 3 of DoDI 5000.02 requires that the Life-Cycle Sustainment Plan (LCSP) will: Correct Answer: Describe sustainment influences on system design and the technical, business, and management activities to develop, implement, and deliver a product support package.
BIT (built in test) Correct Answer: Component enables the system to conduct a self-test to determine if the system is functioning properly.
70-80% of a system's entire cost is during the operation and support (O&S) cycle. Correct Answer:
Reliability defined: Correct Answer: How long an item or system will perform its function before it breaks. The term MTBF is used to quantify and measure reliability and is defined in the Capability Development Document (CDD).
Reliability is a mandatory Key Systems Attribute (KSA) for: Correct Answer: ACAT I programs. For ACAT II programs and below, the user representative (service sponsor) will determine applicability.
MTTR (Mean Time To Repair) Correct Answer: Used to quantify and measure maintainability.
Material Availability (Am): Correct Answer: Is a mandatory Key Performance Parameter (KPP) and is contained in the Capability Development Document (CDD).
(Am) is defined as: Correct Answer: the measure of the percentage of the total inventory of a system operational cable of performing an assigned mission given material condition.
Reliability, maintainability, and supportability are critical factors in achieving: Correct Answer: maximum Operational Availability (Ao)
The primary purpose of the Future Years Defense Program (FYDP)? Correct Answer: Display the manpower, force structure, and funding of the DoD.
The Planning, Programming, Budgeting and Execution (PPBE) process provides a process by which the DoD can: Correct Answer: Identify the fiscal needs of the services and decide how to allocate resources.
During the annual PPBE Programming activity, each service and defense agency submits: Correct Answer: Their POM (program objectives memorandum) to the OSD.
What funding policy applies to the procurement appropriations category? Correct Answer: Full Funding
PPBE Correct Answer: Is the primary resource allocation process for DoD. The PPBE is an iterative, calendar-driven process that operates in one year year cycle.
Programming phase Correct Answer: Translates planning decisions and OSD programming guidance into detailed allocation of time-phased resource requirements.
The primary building block in the PPBE process: Correct Answer: Future Years Defense Programming (FYDP)
FYDP Correct Answer: It sis the single database [Show Less]