What can be defined as an interdisciplinary approach and means to enable the realization of successful systems?
(Choose 1)
A. System of systems
B.
... [Show More] Systems Engineering
C. Project Management
D. Enabling Systems - ✔✔ B.
Which of the following are challenges that influence the development of systems of systems? (Choose 3)
A. System elements cannot operate independently
B. System elements operate independently
C. Engineering hindering development
D. Management hindering engineering
E. Determining system boundaries - ✔✔ B.
D.
E.
During which of the following Life Cycle Stages is the most cost incurred to extract defects? (Choose 1)
A. Concept
B. Development
C. Production
D. Utilization - ✔✔ D.
Every system or product life cycle consists of which three aspects? (Choose 3)
A. Business aspect (business case)
B. Comic aspect (funny)
C. Budget aspect (funding)
D. Technical aspect (product)
E. Marketing aspect (advertising) - ✔✔ A.
C.
D.
The development stage includes which three activities? (Choose 3)
A. Detailed planning
B. Development activities
C. IV&V activities
D. T&E activities
E. AT&T activities - ✔✔ A.
B.
C.
Which two of the following best represent the role of a Systems Engineer throughout a project's life cycle? (Choose 2)
A. Integrate and test the end product
B. Identify and mitigate risks
C. Perform quality audits and collect metrics
D. Assure the proper involvement of domain experts
E. Control budget and schedule - ✔✔ B.
D.
On which type of project would one use an incremental & iterative development (IID) development stage approach? (Choose 1)
A. Project where it is necessary to coordinate large teams of people working in multiple companies
B. Project requiring thorough requirements traceability and verification
C. Project with high rate of unforeseeable change
D. Project requiring completeness of documentation - ✔✔ C.
Identify three purposes of the Resource Management Process. (Choose 3)
A. Create and maintain a pool of resources for projects
B. Provide mechanisms to inform the enterprise infrastructure of projects resource needs
C. Develop system life cycle process guidelines
D. Allocate budgetary and investment resources
E. Manage personnel to staff projects - ✔✔ A.
B.
E.
What are two purposes of the Acquisition Process? (Choose 2)
A. To establish an agreement between two enterprises under which one party supplies products or services to the other.
B. Ensure property, data, or information are properly stored, maintained, and accessible to those who need it.
C. To establish an agreement between two enterprises under which one party acquires products or services from the other.
D. To apply due diligence in the selection of suppliers in an effort to avoid failures and impacts to budgets and schedules.
E. To make visible the goals of the enterprise toward customer satisfaction. - ✔✔ C.
D.
Which of the following identifies the four key success factors for Enterprise Processes? (Choose 1)
A. Funding, Management Oversight, Supply Chain, Resources
B. Resources, Accounting, Funding, Scope
C. People, Strategy, Resources, Market
D. Strategy, Market, Funding, Management Oversight - ✔✔ C.
Identify two (2) inputs to the Infrastructure Management Process. (Choose 2)
A. Organization training plan
B. Organization infrastructure needs
C. Project infrastructure needs
D. Project Assessments
E. System Engineering Plan - ✔✔ B.
C.
Which two processes are identified by ISO/IEC 15288 as Agreement Processes? (Choose 2)
A. The Enterprise Environment Management Process
B. The Acquisition Process
C. The Quality Management Process
D. The Supply Process
E. The Investment Management Process - ✔✔ B.
D.
Typical constraints on a system may include: (Choose 2)
A. Mandated use of COTS equipment
B. Operational Interfaces with other systems or organizations
C. Cross-cutting methods
D. Interface control documents - ✔✔ A.
B. [Show Less]