CON 280 Block 1 Quiz, Source Selection and Administration of Service Contracts. 100% Correct Answers The Contracting Officer for a complex services
... [Show More] acquisition team is attending and leading his tea m’s initial meeting. He knows from experience and from DAU classroom training that risk identification is a critical process that will ensure a comprehensive, well-planned acquisition. During which stage of the acquisition lifecycle must risk identification and analysis be performed? Answer Selected Answer: d. During the Review Current Strategy step of the Planning Phase of the services acquisition process, i.e. early and often - a continuous process Correct Answer: d. During the Review Current Strategy step of the Planning Phase of the services acquisition process, i.e. early and often - a continuous process Question 2 2 out of 2 points false You have been assigned to an IPT that will develop the evaluation criteria and will recommend the source selection evaluation methodology for a complex, high-dollar procurement. The market research completed indicates there are a number of potentially viable technical solutions. The Government desires to keep the flexibility to accept other than the lowest priced proposal or other than the highest technically rated proposal to achieve a best-value contract award. Which method of procurement allows this flexibility? Answer Selected Answer: a. Trade-off process Correct Answer: a. Trade-off process Question 3 2 out of 2 points Your program office is formulating the strategy for an upcoming program to acquire Government-unique, operational support services for a period of up to 5 years. The total estimated contract value is approximately $12.5 million. Market research also revealed that all of the likely competitors are new technology firms who do not regularly perform under Government contracts and do not have adequate accounting systems. Given these circumstances, which contract type would you be able to award? Answer Selected Answer: c. Firm Fixed Price Correct Answer: c. Firm Fixed Price Question 4 2 out of 2 points A pre-solicitation conference will be held next month and you are preparing the synopsis to be posted on FEDBIZOPPS. A draft RFP will be posted with the synopsis with a note that conference attendees will be given a CD containing RFP attachments comprising very large, numerous technical files that could not be posted on the internet. Since the program office manages the technical files, the program manager tasked her technical specialist, John Smith, to produce the CDs for distribution at the conference. For those potential offerors or potential subcontractors who cannot attend the pre-solicitation conference but want to request the CD, which person do you identify as the point of contact in the synopsis? Answer Selected Answer: d. The Contracting Officer Correct Answer: d. The Contracting Officer Question 5 2 out of 2 points You are planning for the procurement of an advanced, engineering or operational systems development and first production. The uncertainties of performance are such that they preclude use of a firm fixed-price type of contract. However, they may not be so great as to justify use of a cost-plus-a-fixed-fee contract. In these circumstances, what contract type should be used? Answer Selected Answer: b. Cost Plus Incentive Fee Correct Answer: b. Cost Plus Incentive Fee Question 6 2 out of 2 points If the Government makes a change in the Quality Assurance Surveillance Plan, what will be the impact on the Performance Work Statement? Answer Selected Answer: a. There is no impact since the PWS drives the QASP and not vice versa. Correct Answer: a. There is no impact since the PWS drives the QASP and not vice versa. Question 7 2 out of 2 points The contracting officer has just been informed by the program office of a new $600,000 requirement for services that will be coming his way. This is the first time he has heard of this requirement. When should the contracting officer reach out to the small business specialist for advice and support? Answer Selected Answer: a. Immediately, as the small business specialist should be involved as early as possible in the acquisition process. Correct Answer: a. Immediately, as the small business specialist should be involved as early as possible in the acquisition process [Show Less]