Which of the following is NOT an output of the Control Scope Process?
Change Requests
Work Performance Information
Project Documents Update
Accepted
... [Show More] Deliverables - CORRECT ANSWER Accepted Deliverables
Which of the following are outputs of the Plan Risk Responses Process?
Change requests, project management plan updates, and project documents updates
Risk management plan and risk register
Risk register and risk report
Work performance information, and organizational process assets updates - CORRECT
ANSWER Change requests, project management plan updates, and project documents updates
Which of the following are types of project management office (PMO) structures?
Interactive, integrating, and developmental
Interactive, monitoring, and directive
Supportive, monitoring, and directive
Supportive, harmonizing, and collaborative - CORRECT ANSWER Supporting, controlling, and
directive
Which of the following is an output for the validate scope process?
Validated deliverables
Accepted deliverables
approved change requests
scope baseline - CORRECT ANSWER accepted deliverables
Which of the following best describes analogous duration estimating?
Used to estimate uncertainty and risk of stakeholders
Used as part of three-point estimating
Used to estimate project cost to the greatest level of specified detail
Used to estimate project duration when there is a limited amount of detailed information about
the project - CORRECT ANSWER Used to estimate project duration when there is a limited
amount of detailed information about the project
The Planning Process Group contains which of the following?
The project management processes that occur when the project is being closed
The project management processes that occur when a project is started
The project management processes that occur when the work is carried out
The project management processes that occur when the project is being organized and prepared -
CORRECT ANSWER The project management processes that occur when the project is being
organized and prepared
An activity in a network has the following characteristics: ES=12 weeks, EF= 22 weeks, and
LS= 14 weeks. The duration of the activity is:
14.0 weeks
8.0 weeks
10.0 weeks
12.0 weeks - CORRECT ANSWER 10.0 weeks [Show Less]