Major Capabilities Acquisition Pathway Structure correct answers The structure of a DoD acquisition program and the procedures used should be tailored as
... [Show More] much as possible to the characteristics of the product being acquired, and to the totality of circumstances associated with the program, including operational urgency and risk factors.
Major Capabilities Acquisition Pathway Structure- Milestones correct answers The Major Capability Acquisition pathway uses "milestones" to oversee and manage acquisition programs.At each milestone a program must meet specific statutory and regulatory requirements before the program can proceed to the next phase of the acquisition process.These are the three milestones:
Milestone A: initiates Technology Maturation and Risk Reduction
Milestone B: initiates Engineering and Manufacturing Development
Milestone C: initiates Production and Deployment
Major Capabilities Acquisition Pathway Structure- Phases correct answers 5 phases-
Material Solution Analysis
Technology Maturation and Risk Reduction
Engineering and Manufacturing Development
Production and Development
Operations and Support
Major Capabilities Acquisition Pathway Structure- Decision Points correct answers The Major Capability Acquisition pathway also consists of these four decision points:
Materiel Development Decision (MDD)
Capability Development Document Validation (CDD-V)
Development Request for Proposal (RFP) Release Decision
Full-Rate Production (FRP) Decision
Material Development Decision (MSA) correct answers In the Materiel Solution Analysis phase, we pick the most promising technology to meet the user need identified in the Initial Capabilities Document.(Pick the Most Promising Technology)
Technology Maturation and Risk Reduction (TMRR) correct answers In the Technology Maturation and Risk Reduction phase, we reduce risk by proving the reliability of the technology through competitive prototyping. This ensures that we select the most adequate and compatible technology.Reducing Risk through Competitive Prototyping and Demonstration of Critical Technologies
Engineering and Manufacturing Development (EMD) correct answers In the Engineering and Manufacturing Development phase, we complete the build to design. This involves building a specified number of prototypes based on the selected design to prove that the design works and the technology can be manufactured or produced.
Complete the Build-to Design [Show Less]