1- What does NOT match with Agile Manifesto?
• Process and tools over individuals and
... [Show More] interactions
• Working software over comprehensive documentation
• Responding to change over following a plan
• Contract negotiation over customer collaboration
2- Which of the following statements about changing requirements in software development, are correct?
In traditional way of software development, once the requirements are base lined,
further changes should undergo heavy change control process
•
• Changes are acceptable till design but once development starts, any further changes should be rejected
• In traditional way of software development, once the requirements are base lined, further changes can be easily accepted with light process
Organizations must adapt to rapidly changing market conditions to stay relevant in
business
•
3- Which of the following statements BEST describe why Agile is winning?
• Products produced by an Agile approach are cheaper than those produced by any other approach
Agile increases the chances of delivering early business value to the market and quickly
incorporate the feedback from the market usage
•
• Products have faster time to market but may not meet immediate customer needs
• Products are expensive when compared with products produced by other approaches, but are of top quality.
4- Why were the `practitioners of alternative software development methods` not satisfied with the traditional waterfall method?
• Waterfall is not a lightweight process
• The practitioners did not like to work in a formal system and hence did not like any ‘methodology’ at all
• Waterfall experience did not add value to their resume
Waterfall model failed to meet the demand for speed and was not friendly towards
changing business needs and priorities
•
5- Which of the following BEST represent the Scrum approach to planning?
• Planning is a continuous activity done faintly by Scrum Master and Product Owner
• Detailed planning is done upfront and not revisited
Whole team together does just enough upfront planning followed by continuous
planning throughout the project
•
• Only planning in Scrum is one of the planning events
6- How should work be allocated to the team in a Scrum project?
• The Scrum Master must assign tasks to individuals
• Team members must volunteer for tasks appropriate to their skills
• The complex tasks must be allocated by the Scrum Master
• Tasks must be allocated to team members by the Product Owner
• While senior team members volunteer for tasks, juniors must be assigned takas by the Scrum Master
7- The time box for a Daily Scrum is…
• Two minutes per person
• 15 minutes
• 2 hrs
• No time box
• 30 minutes
8- Why is the Daily Scrum held at the same time and same place?
• So that the place can be named as Daily Scrum Hub
• The consistency reduces complexity and overhead
• The Product Owner demands it
• Rooms are hard to book and this helps in advance booking
• There is no such rule
9- What BEST describe a Scrum Team?
Small but have enough members to create the Product Increment
Collaborate with each other to self-organize their work
•
•
• Team members must be specialists
• Cross Functional
• Reports to Product Owner
10- The Product Owner in a Scrum project….
• Has no control over the prioritization of Product Backlog Items
• Has the final authority over the prioritization of Product Backlog Items
• Collaborates with the developers over prioritization of Product Backlog Items, but the developers have the final say
Collaborates with de developers over prioritization of Product Backlog Items but
Product Owner has the final say
•
• Creates the Product Backlog Items but leaves prioritization to Business Analyst
11- Noor´s Scrum Team Had a great Sprint Review of a new feature wih their Product Owner. Product Owner was happy new feature, and wanted to release the feature to user. But, the Scrum Team cannot do it themselves because production environment is owned the company´s IT operations team. Scrum Team was directed to create a ticket with IT operations for production release, and wait a week a week for an Ops engineer to manually work on the ticket. What is missing in this environment?
• Feedback
• Flow
• Continuous Improvement
12- Which one of these is NOT an XP practice?
• Test Driven Development
• Extreme Reviews
• Pair Programming
• Continuous Integration
• Refactoring
13 – What is a Kanban Board?
Select the correct options(s) and click Submit
• A list of activities banner by the team
• The set of Can Have requirements
• A visible chart depicting the work to be done, work in progress and work done
• Board that captures the details of the entire project for audit purpose
14 – A Scrum Team works on a 4 weeks Sprint. After few Sprints, the team finds that they spend more effort on unit testing, as the code base size has increased. What can be BEST recommended for this team?
Select the correct option(s) and click Submit.
• Unit testing is not fun anyway. As a self-organized team, choose to ignore the unit testing
• Adopt practices like test automation form other frameworks like XP
• Increase the duration of the sprint from 4 weeks to 6 weeks
• Add two more temporary testers
• From a separate Testing team
15 – Design Thinking is another name for Agile Manifesto. Select the correct option(s) and click Submit.
• True
• False
16 Mannar & Company kick started a major cross company project that involved working with multiple business unit leaders to build enterprise wide platform. Impressed by the success of small projects in Agile, company leadership enforced Agile in this transformation project. Shortly after few Sprints, teams witnessed that the Product Owner was not able to build consensus among the business unit leaders on requirements. There were several political aspects behind the collaboration. What went wrong?
• For large transformation projects, Design Thinking is required before Agile
Agile is based on trust and collaboration so that consensus can be arrived at quickly.
This scenario did not have that atmosphere
•
• Agile doesn’t require any pre-requisites. It works very well in all context. In this scenario, the Product Owner doesn´t seem to be competent
17- Which of these are the needed actions to realize TCS vision of “0-4-2”? Select the correct option(s) and click Submit.
• Agile Ready Partnership
• All get Agile Certified
• Agile Ready Workforce
• Top-to-bottom Enterprise Agile Company ourselves
• Agile Ready Workplace
18 – Jerald is a leader of a TCS customer Account. He learnt that the company´s aspiration on Agile is to become 100% Agile by 2020. He gathered his Agile Experts within the account and asked them for a plan to transition from current way of working to 100% Agile way of working as defined in the text book. Jerald correctly understood TCS aspiration. Select the correct option(s) and click Submit.
• True
• False
19- TCS Agile vision ´100% Agile by 2020`means Select the correct option(s) and click Submit.
TCS to be regarded by the market and our customers as 100% right partner/advisor for
Agile Transformations
•
• Every project in TCS must follow all practices of Extreme Programming
• 100% of TCS associates must be at least at Agile E3 Competency
• There should not be any Agile related non-compliance in the project audits
20 - ´Agile for Beginners´ course is intended towards motivating you to learn more about
Agile so that you can become
Select the correct option(s) and click Submit.
• Project Leader
• Agile Practitioner
• Project Manager
• Certified Manager
• None of the above
21- Agile Manifesto has… Values and … principles Select the correct option(s) and click Submit
• 4,10
• 6,12
• 4,12
• 4,4
• 3,5
22- There are two Product Development Teams. Team ToyZon and Team Zon. Team ToyZon follows traditional way and Team Zon follows Agile way of working. Which team has the higher chance to provide early benefits to the customer? Select the correct option(s) and click Submit.
• Team ToyZon
• Team Zon
23 – Which of these is a benefit of Agile?
Select the correct option(s) and click Submit.
• Reduced Risk
• Faster time to market
• Ability to respond to changing requirements
• Improved collaboration between business and technical team
• All of these
24 – Match the framework to its author(s) in the order of listing:
Scrum; Crytal; Extreme programming
Select the correct option(s) and click Submit.
• Kent beck, Alistair Cockburn; Ken Schwaber and Jeff Shtherland
• Ken Schwaber and Jeff Sutherland, Kent Beck, Alistair Cockburn
• Ken Schwaber and Jeff Sutherland, Alistair Cockburn, Kent Beck
• Alistair Cockburn, Ken Schwaber and Jeff Sutherland, Kent Beck
• Takeuchi and Nonaka, Alistair Cockburn, Kent Beck
25 How is the Agile value “Responding to change over following a plan” addressed in Scrum?
Select the correct option(s) and click Submit.
• Product Owner can change the Sprint Backlog any day
During the Sprint Planning, Development team has all the authority to choose any
Product Backlog item to work on
•
• Product Owner writes lightweight Change Requests for quick approvals
Product Owner can change the plan for next Sprint based on latest market conditions
and feedback from last Sprint
•
• Product Owner can change the Product Backlog any time
26- A good Agile team should exhibit the following qualities … Select the correct option(s) and click Submit.
• All in team must have the same level of technical expertise
• The team is self-organizing
• The team should only take up tasks assigned by Product Owner
• The team must be hierarchical with a strict chain of command
• The team is cross-functional
27- On the last day of the Sprint, a Scrum Team named AlmostDone is ready to show their work but requires just 2 more days to complete the testing. What should the Scrum Master recommend?
Select the correct option(s) and click Submit.
• Extend the Sprint by two days so that the team can complete the work
• Close the sprint on time
28- Only these people are allowed to attend Sprint Retrospective Select the correct option(s) and click Submit.
• Scrum Master and Development team
• Product Owner and Development team
• Scrum Master and Product Owner
• Scrum Team
29 – Product Owner and Scrum Master can be the same person Select the correct option(s) and click Submit.
• True
• False
30 Which of these are Agile estimation techniques? Select the correct option(s) and click Submit.
• Full Upfront Estimates
• Planning Poker
• Work Breakdown Structure
• T Shirt sizing
• Random Distribution
31 – Providing additional feature without clear understating of the business need – What is this category of waste?
Select the correct option(s) and click Submit.
• Inventory
• We do it all the time. It is not a waste.
• Over Production
• Defects
• Over Processing
32 Improves the flow of business idea through its development and release to users.
Select the correct option(s) and click Submit.
• Good Requirements Management Tool
• Waterfall method
• DevOps practices
• Beta release
• Change Control Board (CCB)
33 – John, a team member, has completed E0 0 Agile for Beginners. He wants to contribute to TCS Agile Vision. He wants to find out what is planned for his account. Whom should he contact for details?
Select the correct option(s) and click Submit. [Show Less]