BSB51407 - Diploma of
Project Management
Project Scope Management
Questions & Answers
Plus Exercises
Page
|
2
Table of Contents
Table of Contents
.............................................................................................................................
2
Questions for Scope Management
........................................................................................................
3
Answers for Scope Management
..........................................................................................................
7
Exercises - Manage Project Scope
....................................................................................................
8
Responsibilities for project scope activities
......................................................................................
8
Stakeholder involvement in project scoping
........................................................................................
8
Reflection: Scoping a project
............................................................................................................
8
Conduct project authorisation
..............................................................................................................
9
Defining the scope of a project
...........................................................................................................
12
Reflection: Breaking deliverables into manageable chunks
..........................................................
12
Reflection: Conducting a Works Breakdown exercise
...................................................................
13
Clarifying outcomes and establishing performance measures
..........................................................
14
Reflection: Developing a performance review plan
......................................................................
14
Reflection: Improving scope management - Sydney Opera House project
..................................
15
Reflection: Assessing scope effectiveness and recommending changes
......................................
17
Page
|
3
Questions for Scope Management
1.
Of the following, which is not part of project scope management?
a.
Scope planning
b.
Scope verification
c.
Quality assurance
d.
Create WBS
2.
You are the project manager for the HGD Project and will need as many inputs to the scope
planning as possible. Of the following, which one is not an organizational process asset
?
a.
Organisational procedures
b.
Organisational policies
c.
WBS
d.
Historical information
3.
You are a project manager for your organisation. Sarah, a project manager in training, wants
to know which project documents can stem from templates. Your answer should be
?
a.
Risk policies
b.
Organisational policies
c.
Scope management plans
d.
Historical information.
4.
You are the project manager for a technical project. The project product is the complete
installation of a new operating system on 4500 workstations. You have, in your project cost
and time estimates, told the customer that the estimates provided will be accurate if the
Thanks for rating! You should receive an unlock shortly.
Page
|
4
workstations meet the hardware requirements of the new operating system. This is an
example of which of the following?
a.
Risk
b.
Assumption
c.
Constraint
d.
Order of magnitude
5.
You are the project manager for the NBG Project. This project must be completed within six
months. This is an example of which of the following?
a.
Schedule
b.
Assumption
c.
Constraint
d.
Planning process
6.
Which of the following best describes the project scope statement?
a.
The description of the project deliverables
.
b.
The authorising document that allows the project manager to move forward with
the project and to assign resources to the tasks.
c.
A project scope statement focuses on completing all of the required work, and only
the required work, to create the project’s deliverables.
d.
The process of planning and executing all of the required work in order to deliver
the project to the customer.
7.
During the planning phase of your project, your project team has discovered another
method to complete a portion of the project scope. This method is safer for the project
team, but may cost more for the customer. This is an example of:
Page
|
5
a.
Risk assessment
b.
Alternative identification
c.
Alternative selection
d.
Product analysis
8.
Of the following, which does the scope statement not provide?
a.
Project justification
b.
Project product
c.
Project manager authority
d.
Project objective
9.
You are the project manager for the JKL Project. This project has over 45 key stakeholders
and will span the globe when implemented. Management has deemed that the project’s
completion should not cost more than $34 million. Because of the global concerns, the final
budget must be in U.S. dollars. This is an example of which of the following?
a.
Internationalisation
b.
Budget constraint
c.
Management constraint
d.
Hard logic
10.
You are the project manager for your organisation. You need to ensure the customer
formally accepts the deliverables of each project phase. This process is known as
______________________?
a.
Earned value management [Show Less]