Mark determined the project he had been working on for two months was ready to close since all of the contracts were completed.Based on the current
... [Show More] situation of Mark's project, select the next two steps below that he will perform in the closing process.
a.)Refer to governance to determine the documentation left to complete, then obtain feedback to compile lessons learned.
b.)Meet with the project sponsor to gain project approval, then meet with the person responsible for taking ownership.
c.)Refer to governance to determine the documentation left to complete, then meet with the project sponsor to gain project approval.
d.)Obtain feedback to compile lessons learned, then meet with the person responsible for taking ownership. Correct Answer: c.)Refer to governance to determine the documentation left to complete, then meet with the project sponsor to gain project approval.
During a project closing, problems with readiness or impact are evaluated.Which of the following project issues below is an issue with readiness?
a.) Picnic tables for the pavilions need to be delivered and installed.
b.) Some stakeholders feel having a playground in the park is dangerous.
c.) Some citizens are upset that historic buildings were demolished to build the new green space.
d.) Local groups thought the park would include a shelter that could be reserved for events. Correct Answer: a.) Picnic tables for the pavilions need to be delivered and installed.
An artist was commissioned to create original statues and art pieces for display at different points of the walking trails at the local park. The artist planned on creating some controversial pieces and Carson, the project manager, would need more time to work with him on agreeing to new artistic designs. Which of the following descriptions corresponds with the "Close and Deliver As Is" path?
a.) Carson decides to close the project and not continue in any way.
b.) Carson decides to give the artist two more months to finish the pieces. He moves the green space opening date to accommodate the artist.
c.) Carson decides to close the current project. The green space will open on time without any art installations.
d.) Carson decides to close the current project. He scopes the deliverables related to the artist in a separate scope document. Correct Answer: c.) Carson decides to close the current project. The green space will open on time without any art installations.
Kendall must explain the __________ in the project schedule, caused by the additional four days that were needed to make updates to the project deliverables.
a.) overrun
b.) gap
c.) transfer
d.) baseline Correct Answer: a.) overrun [Show Less]