QUESTION 1
An element of the project scope statement is:
A. Acceptance criteria.
B. A stakeholder list.
C. A summary budget,
D. High-level
... [Show More] risks.
Correct Answer: A
QUESTION 2
Which document describes the necessary information to determine if a project is worth the
required investment?
A. Cost baseline
B. Service level agreement
C. Memorandum of understanding
D. Business case
Correct Answer: D
QUESTION 3
Which input to the Plan Risk Management process provides information on high-level risks?
A. Project charter
B. Enterprise environmental factors
C. Stakeholder register
D. Organizational process assets
Correct Answer: A
QUESTION 4
Which item is an example of personnel assessment?
A. Resource calendar
B. Tight matrix
C. Team-building activity
D. Focus group
Correct Answer: D
QUESTION 5
Which input to the Manage Stakeholder Engagement process provides guidance on how
stakeholders can best be involved in a project?
A. Feedback analysis
B. Stakeholder analysis
C. Communication management plan
D. Stakeholder management plan
The Latest PMP Exam ☆ Instant Download ☆ Free Update for 180 Days
Guaranteed Success with EnsurePass VCE Software & PDF File
Correct Answer: D
QUESTION 6
Which input to the Identify Stakeholders process provides information about internal or external
parties related to the project?
A. Procurement documents
B. Communications plan
C. Project charter
D. Stakeholder register
Correct Answer: C
QUESTION 7
The Identify Stakeholders process is found in which Process Group?
A. Initiating
B. Monitoring and Controlling
C. Planning
D. Executing
Correct Answer: A
QUESTION 8
An input to Develop Project Charter is a/an:
A. Business case.
B. Activity list.
C. Project management plan.
D. Cost forecast.
Correct Answer: A
QUESTION 9
Which Knowledge Area involves identifying the people, groups, or organizations that may be
impacted by or impact a project?
A. Project Risk Management
B. Project Human Resource Management
C. Project Scope Management
D. Project Stakeholder Management
Correct Answer: D
QUESTION 10
Which input to Collect Requirements is used to identify stakeholders who can provide information
on requirements?
The Latest PMP Exam ☆ Instant Download ☆ Free Update for 180 Days
Guaranteed Success with EnsurePass VCE Software & PDF File
A. Stakeholder register
B. Scope management plan
C. Stakeholder management plan
D. Project charter
Correct Answer: A
QUESTION 11
In which Knowledge Area is the project charter developed?
A. Project Cost Management
B. Project Scope Management
C. Project Time Management
D. Project Integration Management [Show Less]