How many project management knowledge areas are there in the PMBOK 6th Edition?
- CORRECT ANSWER 10 project management knowledge areas
How many project
... [Show More] management processes are covered in the PMBOK 6th Edition? -
CORRECT ANSWER 49 project management processes
What are the 10 project management knowledge areas? - CORRECT ANSWER
Communications Management
Cost Management
Integration Management
Quality Management
Procurement Management
Resource Management
Risk Management
Schedule Management
Scope Management
Stakeholder Management
What are the 5 project management domains? - CORRECT ANSWER Initiating (8
tasks)
Planning (13 tasks)
Executing (7 tasks)
Monitoring (7 tasks)
Closing (7 tasks)
What are the 8 tasks involved in initiating a project? - CORRECT ANSWER 1. Assess
the project
2. Key deliverables
3. Stakeholder analysis
4. Risks & constraints
5. Project charter
6. Approval of project charter by sponsor
7. Benefit analysis
8. Inform stakeholders
Initiating: Task 1 - CORRECT ANSWER Perform project assessment based upon
available information, lessons learned from previous projects, and meetings with
relevant stakeholders in order to support the evaluation of the feasibility of new products
or services within the given assumptions and/or constraints.
Initiating: Task 2 - CORRECT ANSWER Identify key deliverables based on the
business requirements in order to manage customer expectations and direct the
achievement of project goals.
Initiating: Task 3 - CORRECT ANSWER Perform stakeholder analysis using appropriate
tools and techniques in order to align expectations and gain support for the project
Initiating: Task 4 - CORRECT ANSWER Identify high level risks, assumptions, and
constraints based on the current environment, organizational factors, historical data,
and expert judgement, in order to propose an implementation strategy.
Initiating: Task 5 - CORRECT ANSWER Participate in the development of the project
charter by compiling and analyzing gathered information in order to ensure project
stakeholders are in agreement on its elements.
Initiating: Task 6 - CORRECT ANSWER Obtain project charter approval from the
sponsor, in order to formalize the authority assigned to the project manager and gain
commitment and acceptance for the project.
Initiating: Task 7 - CORRECT ANSWER Conduct benefit analysis with relevant
stakeholders to validate project alignment with organizational strategy and expected
business value.
Initiating: Task 8 - CORRECT ANSWER Inform stakeholders of the approved project
charter to ensure common understanding of key deliverables, milestones, and their
roles and responsibilities. [Show Less]