Your team is building a website that will consist of four new pages of content. Your project plan
... [Show More] has two team members work together to deliver one page of content: one will outline page content while the other does mockups of page layout. Then they will work together to produce the completed page. Which of the following represents a milestone in your project plan?
A completed page of content
A completed mockup of page layout
A completed outline of page content
A completed project plan
A completed page of content
What is the purpose of your project plan?
To identify milestones
To document scope
To keep your project on track
To determine tasks
To keep your project on track
You start a new job as a project manager in the private banking industry. You need to have a basic understanding of topics such as how clients open accounts, back office operations, and how trade confirmations are verified. Which of the following terms refers to the knowledge you need?
1 / 1 point
Intellectual property
Enterprise learning
Competitive intelligence
Domain knowledge
Domain knowledge
When populating your project plan with a set of tasks, when is the best time to hold a group brainstorming session with team members to help identify tasks? Select all that apply.
After you research your project online
After you review project documentation
After brainstorming a task list with senior stakeholders
Before you do any other project work
After you review project documentation
After you research your project online
You have gathered information from project documentation and the project team. With this information, you identified and created a list of tasks for your project plan. What is the next step for completing your project plan?
Identify points in the project plan where you can evaluate completed work. F
Identify tasks that carry a high risk. (F)
Identify the order in which tasks need to be completed.
Identify tasks that stakeholders have a particular interest in.
Which of the following may indicate a milestone for your project?
A task that has a major impact on the project's overall progress
A task that involves the fewest dependencies (F)
A task that has the highest confidence ratings
A task that your team has the most experience with
A task that has a major impact on the project's overall progress
What term refers to a time estimate that only takes into account the actual time it takes to complete a task?
0 / 1 point
Taskflow duration estimate
Total duration estimate (F)
Effort estimate
Milestone estimate
Which of the measures involved in “three-point” time estimations express how long you hope the task will take, assuming everything goes as planned?
0 / 1 point
Milestone time estimates (F)
Most likely time estimates
Planning time estimates F [Show Less]