We have a project (Cardinal), with these activities in days: Activity A
... [Show More] with duration 4 and no
precedents. Activity B with duration 15 and predecessor. A, Activity C with duration 9 and
predecessor. A, Activity D with duration 2 and predecessor B, Activity E has duration 6 and
predecessors B and C, Activity F has duration 4 and predecessor D, and Activity G has duration 15
and predecessors of E and F. Draw this to answer the following questions. How long is this project
scheduled to take? Correct Answer: 40 Days
From question #1, what is the EF for Node E? Correct Answer: 25
From question #1, what is the LF for Node E? Correct Answer: 25
What is the critical path from #1? Correct Answer: A~B~E~G
From question #1, what is the EF for Node D? Correct Answer: 21
From question #1, what is the ES for Node E? Correct Answer: 19
From question #1, what is the LS for Node C? Correct Answer: 10
From question #1, what is the slack in node E? Correct Answer: 0 Day(s)
From question #1, what is the LF for Node D? Correct Answer: 21
From question #1, what is the slack in node D? Correct Answer: 0 day(s)
From question #1, what is the ES for Node C? Correct Answer: 4
From historical data, we know it takes 45 minutes to paint a 100 square foot area. We have to paint a
800 square foot area. How long should we put for the duration of this activity? Correct Answer: 360
minutes
What are the components in the lowest level of the WBS hierarchy collectively called? Correct
Answer: Work Packages
Which estimating technique uses a similar project to predict how long the current project will take to
complete? Correct Answer: Analogous estimating
Ashley, a project manager in your company, is falling behind on the project schedule. She has
elected to crash the project. What is crashing? Correct Answer: Adding additional project resources
to the project activities
Which of the following is normally NOT one of the traditional components of the triple constraint?
Correct Answer: Accepted by the customer
Walking down the hallway, you heard a program manager saying to a project manager, You need the
performance reports to run this process. Which process is the program manager referring to? Correct
Answer: Monitor and Control Project Work
Which organizational structure generally retains team members on it long after they are needed?
Correct Answer: Projectized
In a RACI chart, what does the C stand for? Correct Answer: Consult
Which of the following is FALSE concerning the critical path in a network? Correct Answer: It is the
path that always contains the greatest number of activities
Which of the following is NOT one of the ten project management knowledge areas? Correct Answer:
Project team management
Which of the following scenarios will NOT trigger the closure stage of the project? Correct Answer: A
schedule activity on a critical path is way behind schedule, and there is no way you can meet the
project finish date.
Who creates the WBS? Correct Answer: The project manager with help from the project team
An activity in a network has the following characteristics: LS = 30, duration = 10, and slack is 7. EF =
_____. Correct Answer: 33
Activities with zero time durations are called: Correct Answer: Milestone activities
In which of the following organizational structures does the project manager have the greatest
authority? Correct Answer: Projectized
Which of the following does NOT have to be in the project charter? Correct Answer: Communication
management plan
Of the following, which is the logical order of the project management processes? Correct Answer:
Initiating, planning, executing, monitoring and controlling, closing
What is the difference between weak and strong matrix? Correct Answer: Weak means the functional
manager has more power
What does CAPM stand for? Correct Answer: Certified Associate in Project Management
Three experts gave opinions on how long a task will take to finish. The estimates were 29, 10, and 12
days (in no particular order). What is PERT estimate - ROUNDED? Correct Answer: 15
Which project management process group generally takes the most project time and resources?
Correct Answer: Executing
Three experts gave opinions on how long a task will take to finish. The estimates were 36, 5, and 7
days. What is 3 point estimate? Correct Answer: 16.0