Sheet keynote or reference keynote - CORRECT ANSWER-a notation on a single
drawing sheet
"A facility's "life cycle" includes all of the following
... [Show More] EXCEPT:
a. Project conception
b. Financing
c. Construction
d. Facility management" - CORRECT ANSWER-1. b - PRM 1.4 Life cycle Stages:
Conceptions, Delivery Method, Design, Psrocurement, Construction,
What does CSI's UDS do ? what does it stand for ? - CORRECT ANSWER-UDS
uniform drawing system
CMa stands for... - CORRECT ANSWER-Construction Manager as Advisor
"The objective of the competitive bidding process is:
a. To ensure that all qualified bidders may submit bids on public work projects
b. To ensure that public works contracts are always awarded to the lowest bidders
c. To ensure that the intent of the governing public laws is maintained in the
awarding of contracts
d. To ensure that the cost of the project is reasonable and consistent with the
prevailing conditions in the building industry" - CORRECT ANSWER-2. d - PRM 3.4
What is included in PART 3 of SectionFormat? - CORRECT ANSWER-PART 3-
EXECUTION: describes field/site installation or application, including preparatory
actions and post-installation cleaning and protection. Field/site-built assemblies and
field/site-manufactured products and systems are included.
"A unit price contract or contract portion is used when:
a. Extent of work cannot be fully determined or where actual quantities cannot be
accurately calculated.
b. Extent of work is known, but the owner desires a break-out cost for portions of the
work.
c. It is anticipated that bidders will not examine soil bearing reports prior to submitting
bid.
d. Bidding quantities of equipment.
Review: PDPG 7.1.6.2" - CORRECT ANSWER-"a. Extent of work cannot be fully
determined or where actual quantities cannot be accurately calculated.
Use of unit prices, allowances and alternates should always be limited to those items
required for accurate bidding, in order to keep bidding documents and processes as
simple as possible."
"The contractual relationship governed by the Conditions of the Contract is between:
a. Owner and contractor
b. Architect/engineer and contractor
c. Owner and Subcontractors
d. Owner, contractor, and architect/enginee [Show Less]