CAHIMS Unit Five Questions And
Answers 2023/2024
A/an --operationprogramproject is a temporary endeavor undertaken to create a unique
product or
... [Show More] service. - ANS->>project
Which of the following statements best characterizes the relationship between
organizational structures and project management? - ANS->>How projects are
implemented varies depending on the organization's structure
Which of the following represents indirect costs to a project? - ANS->>Administrative
staff, rent, electricity, and software licensing fees
The category of drivers of HIT projects referred to as --market demandsbusiness
requirementscustomer requests includes legal and regulatory requirements along with
clinical advances. - ANS->>Buisness requirements
--Continuous quality improvementQuality assuranceQuality control is characterized as
work performed on a project that is assessed on the basis of defined standards,
resulting in adjustments to the project's plan when the standards are not met. - ANS-
>>Continuous quality improvement
Tashiana is a savvy project manager. In preparing a weekly status report for the
stakeholders on a large HIT project, she realizes that a few project team members
across three different departments are exceeding their budgeted hours for the past
week. After talking with a member from each department, she realizes that they are all
working on a deliverable that is not part of the original project plan. How should
Tashiana approach this situation? - ANS->>Tashiana should submit a change request
and make adjustments to the project plan only if the request is approved by the
stakeholders
True or false? Because of the complexity, vast scope, and importance of meaningful
use requirements requirement, it was important for health IT project managers to be
aware of meaningful use requirements. - ANS->>true
The stakeholders on a particular HIT project have asked the project manager, Sherie,
for the earliest possible completion date of the project. Which one of the following will
Sherie find the most useful for obtaining this information? - ANS->>Gantt chart project
schedule
Which of the following best describes probability as it pertains to risk management? -
ANS->>probability refers to the chance of a risk event occurrence
Which of the following would be the best way to inform individual team members of the
big picture—of why others do what they do and how each member's activities contribute
to the overall project? - ANS->>For the project manager to collaborate with the project
team to create the project management plan, including determining roles and
responsibilities
George is a certified project manager that Valley View Family Physicians hired to
oversee its EHR implementation project. Which of the following should George use to
compare actual costs to budget forecasts in order to identify discrepancies related to
project costs? - ANS- [Show Less]