ACQ 1010 MODULE 3 EXAM DEFENSE ACQUISITION SYSTEM
What decision authorizes entry into the Production and Deployment phase
Answer Milestone C
... [Show More] decision
Before a project enters the TMRR phase, the AoA must be completed and the Acquisition
Strategy (AS) is approved by the MDA.
Answer True
The Acquisition Strategy (AS) is
Answer Prepared by the Program Manager (PM) during the Materiel Solution Analysis Phase (MSA) and is submitted
to the Milestone Decision Authority (MDA) at Milestone A
When is the Acquisition Program baseline (APB) prepared
Answer Prepared at program initiation and revised to subsequent milestone reviews, program restructuring, or
unrecoverable deviations
What authorizes entry into the Engineering and Manufacturing Development (EMD)
phase
Answer Milestone B decision
What authorizes entry into the Production and Deployment phase
Answer Milestone C decision
What are the major efforts of the Operations and Support phase
Answer Life Cycle Sustainment and Disposal
DoD defines and validates requirements through the Joint Capabilities Integration and
Development System (JCIDS) and develops technology, produces weapons systems, and
provides logistics support through the Major Capability Acquisition pathway.
Answer True
The Office of the Under Secretary of Defense (A&S) asks the Director, International
Cooperation (A&S IC), Defense Advanced Research Projects Agency (DARPA) and the
Military Departments to identify and pursue cooperative opportunities in an emerging
technology area on a global basis to enhance our coalition capabilities. This initiative
supports the achievement of which DoD Security Cooperation objective
Answer International Armaments Cooperation
This study source was downloaded by 100000812546443 from CourseHero.com on 11-22-2023 030322 GMT -0600
httpswww.coursehero.comfile82544033ACQ-1010-Module-3-Exam-Defense-Acquisition-Systemdocx
Paula Smith
ACQ 1010 MODULE 3 EXAM DEFENSE ACQUISITION SYSTEM
Which International Acquisition and Exportability objective addresses the need to
strengthen domestic and allied defense industrial bases
Answer Industrial
The Material Solution Analysis Phase (MSA) ends when the Analysis of Alternatives
(AoA) has been completed, a material solution option for the capability need is
recommended, and the phase-specific entrance criteria for the initial review milestone
have been satisfied.
Answer True
The Operations and Support Phase begins after the production or deployment decision
and is based on which Milestone Decision Authority (MDA) approved document
Answer Life Cycle Sustainment Plan (LCSP [Show Less]